Boreholes

Main Projects -Rehabilitation of Boreholes

Rehabilitation of Ein Haroush Pumping Station in Al Fejeh- Rural Damascus

Description of Contract: The works include:

Mechanical works: Supply and installation of Submersible pumps sets with all mechanical accessories and pipeline as following:

  • Submersible pumps set 1000 m3/h (1 set) with accessories and piping system 500 mm
  • Submersible pumps set 500 m3/h (2 set) with accessories and piping system 300 mm

to provide needed water with a total pumping capacity of 2000 m3/h

Electrical works:

  • Supply and installation of Generators sets 800 KVA (1 Set) and 500 KVA (1 Set) with all electrical accessories
  • Supply and installation electrical panels and Cables
  • Supply and installation Electrical Carne 15 Ton and Electrical valves

Civil works:

Rehabilitation of the pumping rooms and the all station

The concrete works related to the generator set bases and the manholes and inspection rooms

The isolation works for all station roofs 

With: ICRC

City: Damascus

Year:2017

Rehabilitation of 9 boreholes in Rural Damascus in 3 Location

Description of Contract: The works include supply and installation of

Mechanical Equipment’s: Submersible pump sets (9 sets) with the valves well head connections, pipes and all mechanical auxiliary equipment

Electrical Equipment’s: Control panels, Generator sets (150 KVA -1 SET) – (200 KVA -1SET), Cables

And all equipment are necessary to provide needed water for 9 boreholes in Three Location (5 in Al-Tal, 2 in Al-Gezlanyehe , 2 Al-Rehaybe).

With: UNICEF

City: Damascus

Year:2022

Rehabilitation of the Pumping Stations and Drinking Water Wells in Al- Qamishli

Description of Contract: The works include supply and installation of

Mechanical works: Supply and installation of Submersible pumps sets with all mechanical accessories and pipeline as following:

  • Submersible pumps set (5 set) with accessories and piping system
  • Horizontal pumps set (4 set) with accessories and piping system
  • PE Piping system 90 mm (length: 2.5 km).

Electrical works:

  • Supply and installation Transformers 100 KVA (5 Set) and 50 KVA (2 Set) with all electrical accessories with implementation of MV line 5/80 (length 5 km) with the metal bridges
  • Supply and installation electrical panels and Cables

Civil works:

The concrete and excavation works related to the boreholes, piping system and Electrical works .

With: UNDP

City: Al-Qamishli

Year:2020

Equipping Four Boreholes with Pipeline Connection in Jaramana

Description of Contract: The works include supply and installation of

Mechanical works: Supply and installation of Submersible pumps sets with all mechanical accessories and pipeline as following:

  • Submersible pumps set (4 set) with accessories and piping system for 4 boreholes
  • PE Piping system 110 mm (length: 560 m and 630 m).

Electrical works:

  • Supply and installation Generator Set 200 KVA (2 Set) and 45 KVA (1 Set) with all electrical accessories
  • Supply and installation electrical panels and Cables

Civil works:

The concrete and excavation work related to the boreholes, piping system and Electrical works.

Construction of Generator room for the generator 200 KVA .

With: ICRC

City: Rural Damascus

Year:2017

Rehabilitation of 7 deep boreholes in 7 Locations in Sweida government

Description of Contract:

Mechanical works: Supply and installation of Submersible pumps sets with all mechanical accessories and pipeline as following:

Submersible pumps set (7 set) -Capacity: (125 hp-150 hp) with accessories and piping system 7 deep Wells -Depth (600-650 m)

Electrical works:

Supply and installation Transformers 200 KVA (7 Set) with all electrical accessories with

Supply and installation electrical panels and Cables

Civil works:

The concrete and excavation work related to the boreholes, piping system and Electrical works.

With: UNICEF

City: Swieda

Year:2023/2024

Rehabilitation of Sector Five Drainage System in Der Al Zour

Description of Contract:  the work includes:

  • Rehabilitation of Sector Five Drainage System length 204 km
  • Rehabilitation and installing of 33 Agricultural Drainage Wells (Pumps, Piping system)
  • installing the 33 Electrical transformers 200 KV with installing the accessories and MV Line.

Country: WFP

City: Der AlZour

Year:2024